- Opening and approval of agenda
- Schedule of FT2022-1
- Secretariat updates
- Updates on specific activities
- Review of GRIB proposals
- Review of BUFR proposals
- Review of Common Code Tables proposals
- AOB
- One 2-hour meeting to confirm schedule: September 13
- Deadline for submission of proposals: September 30
- Two 2-hour meetings to review new proposals: October 5-6, 12-14 UTC
- Two 2-hour meetings to conclude the proposals: November 9-10, 12-14 UTC
- Deadline for validation (if not completed by the meeting above): December 11
- One additional meeting to finalize remaining issues if necessary: December 14
- National Focal Point review: mid-January 2022
- WMO adoption process: mid-March 2022
- Codes are officially operational: mid-May 2022
- Standard development for uncrewed aircraft observations: new activity (deferred)
- (EF) the 2nd meeting will take place tomorrow and (MK) they will use marine trajectories in NetCDF as a starting point and they will take a look at what needs to be represented in BUFR (EF) don't think there will be a need for Fast-Track right now. It would be good if Marijana could provide updates as it progresses.
- MoC draft available at https://community.wmo.int/activity-areas/wis/wis-manuals
- Normalization of notes
- DAYCLI BUFR sequence: status update
- (JH) this was deferred to this FT cycle. the latest sequence is in the GitHub issue. the precision of the time period has changed and they are now producing some sample data from real data for validation. (SF) there is a sample available on the issue as a start. There was a discussion about whether the time should be local or UTC. After checking with current practices, it was determined to use UTC.
The list of issues proposed so far, divided into substantial ones and those with editorial nature.
No. | GRIB2 | Issue | Assignee | Status |
---|---|---|---|---|
1. | Issue 89 | surface adjusted wind (UK) | Richard | pending |
2. | Issue 106 | code table 4.2: new hydrological parameters, part 2 | Sébastien | Reviewd by hydrological experts |
3. | Issue 108 | Convective lightning potential index | Sibylle | Checking status |
4. | Issue 109 | code table 4.2 height (agl) and altitude (amsl) disambiguation | Mark | |
5. | Issue 110 | Code Table 4.201: changing entry 0 "reserved" to "no precipitation/none" | Sébastien | |
E 1. | Issue 113 | Fix Typo in PDT 4.53 and 4.54 | Anna | Only CSV?, branch will be created |
E 2. | Issue 115 | Fix typo in Code Table 4.246 | Anna | Only CSV, branch will be created |
E 3. | Issue 116 | unit of vorticity in code table 3.15 | Anna | Both PDF and CSV, branch will be created |
E. 4 | Issue 117 | fix code table 4.248 formatting | Anna | Only CSV, branch will be created |
The list of issues proposed so far, divided into substantial ones and those with editorial nature.
No. | BUFR4 | Issue | Assignee | Status |
---|---|---|---|---|
1. | Issue 51 | BUFR sequence for DAYCLI | Sergio | Checking format using sample data. |
2. | Issue 78 | Proposal for BUFRCREX_CodeFlag_en_40.csv | Daniel | |
3. | Issue 83 | New entries of Code Table 0 01 036 (UK) | Anna | |
4. | Issue 85 | New BUFR template for the GIIRS (Geostationary Interferometric Infrared Sounder) observations | Marijana | |
E 1. | Issue 80 | CodeFlag 031031 is missing EntryName value | Anna |
The list of issues proposed so far, divided into substantial ones and those with editorial nature.
No. | CCT | Issue | Assignee | Status |
---|---|---|---|---|
1. | Issue 63 | Add new entries to C-5 to identify HY-2D, FY-3E and FY-4B satellites of China | Fang | |
2. | Issue 64 | Add a new entry to C-2 for radiosonde of China | Fang | |
E 1. | Issue 61 | Correction of spelling: milimetre in C08.csv | Anna | Correction will be made both in PDF and CSV, branch will be created |
- When a new proposal (issue) is created, the issue is generally assigned to the person who makes the proposal and put in "submitted" status.
- Once the team agrees to the general approach and decides to go to validation status, chair moves the issue to "in validation" status and the Secretariat creates a branch. If further discussion is necessary, the issue is moved to "in discussion" status.
- Once the team agrees to the final proposal, asignee consolidates the finalized the proposal in the original post, updates the branch, and post a comment saying "branch updated" with mention to Chair and the Secretariat. (Please do not change issue status.)
- Chair confirms that the proposal is finalized and the associated branch is updated, and moved the issue to the "validated" status.
- A seminar on weather radar will be held September 27 and 29, an invitation will be sent to TT members.
No. | Name | Agency | Sep. 13 |
---|---|---|---|
1 | Jitsuko HASEGAWA | JMA | X |
2 | Enrico FUCILE | WMO Secretariat | X |
3 | Abderrazak LEMKHENTER | Météo Maroc | X |
4 | Fang ZHAO | CMA | X |
5 | Sergio Henrique Soares FERREIRA | National Institute for Space Research, Brazil | X |
6 | Tom KRALIDIS | Environment and Climate Change Canada | |
7 | Jeffrey ATOR | NOAA | X |
8 | Sibylle KREBBER | DWD | X |
9 | Richard WEEDON | Met office | X |
10 | Sébastien VILLAUME | ECMWF | X |
11 | Marijana CREPULJA | ECMWF | X |
12 | Simon Stuart ELLIOTT | EUMETSAT | |
13 | Marian MAJAN | HMEI | |
14 | Anna MILAN | WMO Secretariat | X |
15 | Xiaoxia CHEN | WMO Secretariat | |
16 | Dave BERRY | WMO Secretariat | X |