- Reach First Public Working Draft of a specification for SPC by end of August 2021
- Ship SPC in Chromium by end of October 2021
- Describe and prioritize user stories.
- Establish a feature scope for SPC and prioritize features to appear in a FPWD. Note: subsequent drafts may include different features depending on ongoing WG discussion.
- Develop an API specification (whether part of Payment Request API or a separate API).
- Develop corresponding tests
- Take into account experiences from pilots
- Ship code in Chromium
Also:
- To enable the 3DS use case we will work with EMVCo
Notes:
- Some work will be done in parallel:
- Spec work is likely to begin while requirements are still in development; we will align work as we go
- Coding is likely to be happening in parallel with everything else
- Pilot projects will ideally contribute to the issues list, API requirements, and more. Feedback along the way will be very valuable.
- In addition, we will be working on Payment Request API, the WPWG Charter, and TPAC planning. Those activities are shown in parentheses.
- Mid-May: Identify editing and test suite development resources
- Mid-May: Finalize initial list of user stories. Prioritize them.
- Mid-May: First draft of SPC requirements.
- Late May: Stabilize scope.
- Early June: (Re-Publish Payment Request API 1.0 as a CR)
- Mid-June: Stabilize requirements.
- Late June: First sketch of API, and ideally an updated explainer.
- Early July: Understand which issues need to be addressed before FPWD and which should be highlighted for review in FPWD.
- 10 Aug: Call for Consensus to WPWG to publish SPC FPWD
- Late August: Publish FPWD of API.
- Late August: (Begin rechartering process for WPWG with WG review of revised charter.)
- Late August: Announce intent to ship support for SPC in Chromium
Note: EMVCo has indicated that they anticipate support for SPC should be available in EMV® 3-D Secure 2.3, anticipated in Q3 of 2021.
- Early September: Request reviews of WPWG charter from Horizontal groups and W3C Management
- 9 September: Last publications before start of W3C publishing moratorium until 21 September
- Mid-September: Second Origin Trial ends
- Early October: (Start W3C Membership review of charter)
- Early October: Press release with any experimental results.
- 14 October: Last publications before start of W3C publishing moratorium until 2 November
- 18-20 October: (Authenticate Conference in Seattle)
- 18-29 October: (TPAC 2021; hear results from second origin trial)
- Mid-to-Late October: Release date of Chromium with SPC support
- Mid-November: Announce renewed charter