Added cost rate table support when reading from and writing to PMXML files.
Added a getPopulatedFields method to the TaskContainer, ResourceContainer and ResourceAssignmentContainer classes. This will retrieve the set of fields which are populated with a non-null value across the whole project for Tasks, Resources, and ResourceAssignments respectively.
Add START_ON, FINISH_ON constraint types. Deprecate MANDATORY_START, MANDATORY_FINISH constraint types. MANDATORY_START/FINISH are now represented as MUST_START/FINISH_ON. This change allows users to distinguish between START/FINISH_ON and the MANDATORY_* constraints when reading P6 schedules.
Improve handling of cost rate tables and availability tables when writing to an MSPDI file.
Handle P6 databases and XER files with user defined fields of type FT_FLOAT.
Align invalid XER record behaviour with P6.
Handle Planner files which don't contain an allocations tag.
Gracefully handle MPP files with missing view or table data.