feat(dev): add release and versioning guidelines
Signed-off-by: Jose Martins <[email protected]>
- Loading branch information
Showing
1 changed file
with
65 additions
and
2 deletions.
There are no files selected for viewing
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Original file line number | Diff line number | Diff line change |
---|---|---|
@@ -1,4 +1,67 @@ | ||
.. _versioning: | ||
|
||
Versioning | ||
========== | ||
Releases and Versioning | ||
====================== | ||
|
||
Bao Project's repos follow a `semantic versioning scheme <https://semver.org/>`_ where, for each | ||
release, the specific `git commit is tagged <https://git-scm.com/book/en/v2/Git-Basics-Tagging>` | ||
with a label with the form MAJOR.MINOR.PATCH, where each version component is incremented as | ||
following: | ||
|
||
* **MAJOR** version when you make incompatible API changes | ||
* **MINOR** version when you add functionality in a backward compatible manner | ||
* **PATCH** version when you make backward compatible bug fixes | ||
|
||
When incrementing a given version, the lower order components must be set to 0. | ||
|
||
To illustrate, a project in its `2.3.1` version might: | ||
|
||
* bump to `2.3.2` if a given bug is patched; | ||
* go to `2.4.0` when adding new features that don't break interface compatibility; | ||
* tag `3.0.0` when adding new features that break interface compatibility; | ||
|
||
Release Cycle | ||
------------- | ||
|
||
Bao's Project releases follow a loosely time-based cycle. The expected release cadence, | ||
specifically, bumping the **MINOR** or **MAJOR** versions, is expected to be every 4 to 8 months, | ||
depending on the number of contributions on that given period. That is, if the number of | ||
contributions does not justify a release bump, the release can be postponed to a maximum of 8 | ||
months. | ||
|
||
Each release cycle is essentially composed by two stages: | ||
|
||
* the **development stage**, where the normal development process goes on, PRs with either new | ||
features, fixes or other are submitted, reviewed and merged asynchronously, following the | ||
:ref:`contribution guidelines <contributing>`. | ||
|
||
* during **stabilization stage**, the contributions made during the development stage should be | ||
thorougly tested with the most comprehensive test batteries available. Further, integration tests | ||
may be added at this point. Besides new tests, maintainers must stop accepting PRs that are not | ||
bug fixes or documentation. This stage is expected to last between 2 to 8 weeks, so maintainers | ||
should be aware to stop the development stage after a maximum of about 6 months depending on the | ||
ammount of new contributions. More contributions will require a longer pre-release stage. | ||
|
||
At the end of the release cycle the version is tagged and the process starts all over again.s | ||
|
||
At any point during the release cycle **PATCH** version increments can be tagged to fix bugs, | ||
especially safety hazards or security vulnerabilities. | ||
|
||
|
||
Release Manager | ||
--------------- | ||
|
||
For each release cycle one of the repo's maintainers (ideally always the same), should be elected | ||
the **release manager**, which will be responsible for: | ||
|
||
* deciding when the stabilization stage begins and ends; | ||
* coordinating other maintainers during the stabilization phase; | ||
* tagging and pushing the version to the repo; | ||
|
||
|
||
Submodule Management | ||
-------------------- | ||
|
||
Upon a release tagging, each submodule in the repo should be pointing to a specific release of the | ||
submodule's repo. This may require that a repository's release cycle to be somewhat synchronized to | ||
the release cycle of its submodule dependencies. |