Notifications
You must be signed in to change notification settings - Fork 93
Commit
This commit does not belong to any branch on this repository, and may belong to a fork outside of the repository.
Add dev doc about worker unallocated distribution (#5041)
Co-authored-by: Sam Doran <[email protected]>
- Loading branch information
Showing
1 changed file
with
43 additions
and
0 deletions.
There are no files selected for viewing
This file contains bidirectional Unicode text that may be interpreted or compiled differently than what appears below. To review, open the file in an editor that reveals hidden Unicode characters.
Learn more about bidirectional Unicode characters
Original file line number | Diff line number | Diff line change |
---|---|---|
@@ -0,0 +1,43 @@ | ||
# Distributing Cost | ||
Our cost model allows user to distribute the their costs bassed of the CPU or memory usage of their user projects. | ||
|
||
## Worker Unallocated Costs: | ||
|
||
### How We Calculate | ||
|
||
During data processing we add in additional rows to represent the [worker unallocated](https://github.com/project-koku/koku/blob/main/koku/masu/database/trino_sql/reporting_ocpusagelineitem_daily_summary.sql) cost. These rows are added under the project name `Worker unallocated` during the OCP daily summary table creation. Formula: | ||
``` | ||
unallocated_worker_cost = capacity - effective usage | ||
``` | ||
The effective usage is the `max(request, usage)`, since users can have a higer usage than their request. | ||
|
||
### How We Distribute | ||
|
||
One of the features of our cost models is to distribute the cost associated with the `Worker unallocated` project to the user projects with this algorithm: | ||
``` | ||
distributed_cost = (user_project_usage / usage_of_all_user_projects) * worker_unallocated_cost | ||
``` | ||
|
||
For example, there are worker unallocated cost of 100 dollars and two user projects, A and B. Project A has a usage of 25 and project B has a usage of 75. Using the algorithm above to distribute the worker unallocated cost: | ||
|
||
``` | ||
worker_unallocated_cost = 100 | ||
Project's A distributed_cost = (25 / sum(25 + 75)) * 100 = 25 | ||
Project's B distributed_cost = (75 / sum(25 + 75)) * 100 = 75 | ||
``` | ||
|
||
Project A gets an additional 25 dollars and Project B gets an additional 75 dollars due to distributing the worker unallocated cost. | ||
|
||
**How we deduplicate** | ||
|
||
The `Worker unallocated` project that we created earlier in the *How We Calculate* section still holds the original cost. Using the example above this would be our original 100 dollars. In order to deduplicate costs for the `Worker unallocated` project we need to subtract the unallocated costs: | ||
|
||
``` | ||
distributed_cost = 0 - worker_uanllocated_cost | ||
``` | ||
|
||
Working with our same example: | ||
|
||
``` | ||
Worker unallocated project's distributed_cost = 0 - 100 | ||
``` |