In sdk 1.12 the new "source" field has been added for the BT-806 and BT-821 nodes. Thanks in advance, |
Beta Was this translation helpful? Give feedback.
Replies: 1 comment
-
Hi, |
Beta Was this translation helpful? Give feedback.
Hi,
"epo-notice" is used to indicate that the corresponding criteria will be found in the notice itself. When the notice is identified as a source for criteria, then these criteria have to be specified in the notice.
"epo-procureent-document" is used to indicate that the corresponding criteria are defined in the Procurement Document.
KR